Structurack conceptualized the layout of the storage systems for the expansion of the only canadian distribution center of L’Oréal located in the Saint-Laurent borough. Our team is currently working on the installation of these systems. Thanks to all our partners in this project!
The project in figures:
- 95,000 square foot expansion
- More than 20,000 pallet locations created
- 54 semi-trailer trucks (53′) required to transport components
- 12 weeks installation time